Florida Milestone Inspections After Surfside: What the Law Requires and What Engineers Check

Florida milestone inspection: what the law requires of condominium buildings

When Champlain Towers South in Surfside collapsed on June 24, 2021, 98 people died. Florida then wrote a statewide rule that older condominium buildings must be inspected by a licensed engineer or architect on a fixed schedule. Condo owners, buyers and engineers now meet the phrase "milestone inspection" every week. This guide goes through what the statute says, what an engineer actually does in each phase, and which claims about the results you should read with care.

Quick answer: under Florida Statute 553.899, a condominium or cooperative building of three or more stories needs a milestone inspection by December 31 of the year it turns 30 years old, then every 10 years. A local agency can set 25 years where conditions such as nearness to salt water call for it. Phase one is a visual examination. Phase two, with possible destructive or nondestructive testing, is required only if phase one finds substantial structural deterioration.

Which buildings and when

The statute text applies the rule to a building three stories or more in height, as determined by the Florida Building Code, that is a residential condominium or cooperative in whole or in part. The age is counted from the date the certificate of occupancy was issued. The statute includes transition dates for buildings that were already old when the law took effect. Check the current text and your local agency's notice for your exact deadline, because several laws have amended this section since 2022.

Flowchart of the two phases of a Florida milestone inspection
The two phases, simplified from the statute text.

Phase one: a visual examination

The statute says the architect or engineer performs a visual examination of habitable and nonhabitable areas, including the major structural components, and gives a qualitative assessment of the structural conditions. The license must be Florida's, under chapter 481 (architects) or chapter 471 (engineers). Phase one must be completed within 180 days after the owner receives the written notice from the local agency. The sealed report, with a separate summary of material findings and recommendations, goes to the association, any other owner of part of the building, and the building official.

The key definition: "substantial structural deterioration"

Whether phase two happens depends on this term, and the statute defines it. It means substantial structural distress or substantial structural weakness that negatively affects a building's general structural condition and integrity. The definition adds that the term does not include surface imperfections such as cracks, distortion, sagging, deflections, misalignment, signs of leakage or peeling finishes, unless the licensed engineer or architect determines that such imperfections are a sign of substantial structural deterioration.

That sentence is the most useful thing to understand as an owner. A crack in a wall is not by itself a failed inspection. The same crack can still trigger phase two if the engineer judges that it points to real distress in the structure. The call belongs to the professional, within what the statute calls "a reasonable professional probability based on the scope of the inspection."

Phase two: testing and a repair program

If phase one identifies substantial structural deterioration, phase two must be done. The statute lets the inspector use destructive or nondestructive testing, as extensive or as limited as needed to assess the areas of distress, confirm that the building is structurally sound and safe for its intended use, and recommend a program for assessing and repairing the damaged parts. When choosing testing locations, the inspector must prefer locations that are the least disruptive and most easily repairable while still representative of the structure.

The report also has to describe the extent of any substantial deterioration and recommend repairs. It must recommend remedial or preventive repair for items that are damaged but are not substantial structural deterioration. That last point means a phase one report can be clean on safety and still carry a maintenance list.

What the numbers say, and what they do not

Recording Law reported on November 14, 2026 that OPPAGA, the Florida Legislature's research office, counted 54 buildings that inspections declared unsafe or uninhabitable: 30 in 2024 and 24 in 2025, across eight counties. The same article says state law does not define either term, that building officials reported most of those buildings were not vacated, and that the city of Aventura disputes 19 of the listed buildings. Read the number as an official count of listings, not as 54 buildings in imminent danger.

Bar chart: 30 buildings in 2024 and 24 in 2025 listed unsafe or uninhabitable by Florida inspections
OPPAGA count as reported by Recording Law, with the caveats from the same report.

On the cause of the Surfside collapse, Recording Law quotes the NIST advisory committee from September 2026 as stating that the principal causes were original design and construction deficiencies, and that other issues were opportunities to improve codes and standards rather than evidence that comparable buildings are broadly unsafe. According to the same article, NIST's final report was still being written as of November 10, 2026. Treat any claim about the collapse that goes beyond that as unconfirmed until the final report is out.

The reserve study that goes with it

The inspection is half of the framework. A Florida condo law firm's September 2026 summary says that structural integrity reserve studies are required under section 718.112(2)(g), that after the 2025 amendments (HB 913) the study may be done together with a milestone inspection due on or before December 31, 2026, and that no required study may be completed after that date. We have not read the statute text for the reserve study ourselves, so confirm the details with your association's attorney.

What owners, buyers and engineers should do

  1. Owners: ask the association for the sealed inspection report and its summary, and read the recommendations for items that are damaged but not substantial deterioration, because that is the maintenance forecast.
  2. Buyers: request the phase one report, any phase two report and the reserve study before closing. A law firm summary quoted above says lenders increasingly ask for them.
  3. Engineers: write the scope and limits of the visual examination into the report, since the statute ties the conclusion to "a reasonable professional probability based on the scope of the inspection."

For how an engineer thinks about cracks in general, see AI-driven structural auditing and concrete crack analysis. Readers who also read Arabic can use our guide to when wall cracks are serious and the explanation of why reinforcing steel corrodes in concrete.

FAQ

Does a crack mean my building failed the inspection? No. The statute excludes surface imperfections such as cracks from the definition unless the engineer or architect finds they are a sign of substantial structural deterioration.

What is phase two? A deeper investigation, with possible destructive or nondestructive testing, that the statute requires only when phase one finds substantial structural deterioration.

How often is the inspection repeated? Every 10 years after the first, per the statute.

Caveat: this is an educational summary, not legal or engineering advice for a specific building. The statute text and your local enforcement agency control the deadlines.